The City of Holdfast Bay is undertaking essential upgrades at the Colley Terrace roundabout, Glenelg. These upgrades aim to improve pavement conditions, safety, and stormwater infrastructure. To minimise disruption, the works will be delivered in stages under managed road closures.

Kent Civil Pty Ltd has been engaged to deliver these works, which are scheduled to commence the week of 12 May 2025, with completion expected by the end of June 2025, weather permitting.

Working hours: 7am to 5pm, Monday to Friday.

Construction Staging and Traffic Management:

  • Stage 1 (Approx. 3 weeks)
    Southern lanes closed to through traffic – access for local traffic only. Eastern, Western, and Northern lanes will remain open.
    See map for stage 1
  • Stage 2a (Approx. 2 weeks)
    Partial closures of Western and Southern lanes – minimal impact on traffic flow.
    See map for stage 2a
  • Stage 2b (Approx. 2 weeks)
    Continuation of Stage 2a conditions – minimal impact on traffic flow.
    See map for stage 2b
  • Stage 3 (Approx. 1 week)
    Northern lane towards Anzac Highway will be closed. Eastern, Western, and Southern lanes remain open.
    See map for stage 3

Throughout all stages:

  • Jetty Road, Glenelg, Augusta Street, and Chappell Drive will remain accessible.
  • Access to/from Wilson Carpark, Glenelg Surf Life Saving Club, the beach, etc., will be maintained via Jetty Road, Glenelg, and Augusta Street.

Affected residents and businesses are being directly notified.

If you have any questions regarding the project, please contact us at 8229 9999 or email mail@holdfast.sa.gov.au.

We appreciate your understanding and cooperation as we work to deliver these essential upgrades with the least inconvenience possible.